Generic Letter 2006-02 Grid Reliability and the Impact on Plant Risk - PowerPoint PPT Presentation

Generic Letter 2006-02 Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power Michael E. Mayfield Director, Division of Engineering April 24, 2006 1 1 Generic Letter 2006-02 Grid Reliability and the Impact on


  1. Generic Letter 2006-02 Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power Michael E. Mayfield Director, Division of Engineering April 24, 2006 1 1

  2. Generic Letter 2006-02 Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power • Tools NRC uses to communicate with licensees: – Information Notices – Regulatory Issue Summaries – Generic Letters – Bulletins – Orders 2 2

  3. Generic Letter 2006-02 Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power • What is the process for issuing a Generic Letter? • Why did the NRC issue a Generic Letter on grid reliability? 3 3

  4. Grid Reliability Generic Letter Status • April 6, 2005, Draft Generic Letter issued for public comment • January 9 and 10, 2006, Federal Energy Regulatory Commission (FERC) participated in NRC public workshop on draft Generic Letter • February 1, 2006, Issued Generic Letter • February 16, 2006, FERC issued Interpretive Order • April 3, 2006, Received Generic Letter responses 4 4

  5. Focus of Generic Letter 2006-02 • Generic Letter focused on Licensees’ capability to: – Monitor grid conditions to determine the operability of offsite power systems – Incorporate grid conditions in the assessment and Incorporate grid conditions in the assessment and – management of risk- -associated maintenance associated maintenance management of risk – Evaluate site Evaluate site- -specific increases in loss of offsite power specific increases in loss of offsite power – frequency and impact on station blackout frequency and impact on station blackout 5 5

  6. Other Activities • Performed assessments of operational readiness of offsite power for nuclear power plants – Temporary Instruction 2515/165 [ML060550258] • Issued a generic communication to inform licensees of a recent NRC study on loss of offsite power events – Information Notice 2006 Information Notice 2006- -06 [ML053200013 06 [ML053200013 – – NUREG/CR NUREG/CR- -6890 [ML060200477, ML060200479, 6890 [ML060200477, ML060200479, – ML060200510] ML060200510] 6 6

  7. Current Assessment • Preliminary results of NRC assessments of operational readiness of offsite power for nuclear power plants • Initial assessment of Generic Letter responses 7 7