gen ve international projets de construction et de
play

Genve international : projets de construction et de renovation - PowerPoint PPT Presentation

Genve international : projets de construction et de renovation Presented by: Veronique Neiss SHP/UNOG Date: 15 Juin 2016 Palais des Nations Second largest UN Office after the UN Headquarters in New York The most active


  1. Genève international : projets de construction et de renovation Presented by: Veronique Neiss – SHP/UNOG Date: 15 Juin 2016

  2. Palais des Nations • Second largest UN Office after the UN Headquarters in New York • The most active centre for multilateral diplomacy relating to Peace, Human Rights and Well- being in the world Working for Peace, Rights and Well-being

  3. Palais des Nations Today • Ariana Park: 46 hectares • Total floor area of entire complex : 234,000m2 (gross) • Total floor area of main buildings: 180,000m2 (gross) • Conference rooms: 34 Original Buildings Constructed 1929-1936: • Number of workplaces: 2,800 • Assembly Rooms (A+AB+AC) • Library & Archives (B) • Delegates: 75,000+/year • Council Chamber Area (C) • • Secretariat Offices (S1+S2) Visitors: 100,000+/year • Meetings: 10,000+/year Extension Building Constructed 1950 -1952: • Offices (D) • Events: 6500/year Additional Building Constructed 1968-1973: • Conference Building (E)

  4. The need for the Strategic Heritage Plan

  5. Existing Condition Electrical panels • End of lifespan installations Air Handling Units • No fire or smoke dampers • Inefficient controls • Some from the 1930’s Archives • Fire safety • Water leaks Old Cinema • Repurposing opportunity from member state donation

  6. Existing Condition Library Archives • Fire safety • Protection of repository for humanity Room XIX • Obsolete congress systems • Fire safety • Disabled accessibility Asbestos Removal • Asbestos applied to structure • Asbestos in miscellaneous materials

  7. Objectives Making our workspace safer and • more flexible. Making our buildings accessible to • persons with disabilities. Reducing our energy costs and • consumption. Preserving the heritage of the • Palais des Nations. Upgrading the IT, broadcast and • congress systems. Maintaining business and • operational continuity Making sure we deliver on time • and on schedule.

  8. SHP Approved by UN General Assembly 2015 The Strategic Heritage Plan (SHP) scope, schedule and budget has now been approved for the following: • Enabling /Site preparation works • Construction of a new office building • Renovation of existing Palais des Nations buildings • Dismantling of E building office tower • Final Completion in 2023 • CHF 836.5 M Approved Total cost • Including use of Swiss loan for CHF 400 M

  9. Governance Structure • High level project owner UN Secretary-General • Strong Governance UNOG • Steering High level support and Director-General Advisory Board Committee Project Owner assistance from Swiss Federal Government, FIPOI, Canton and City of UNOG UN Director of Project Geneva Administration Stakeholders • Experienced International UN specialist project UN Specialist Independent/ UNOG SHP Programme delivery team led by the Integrated Risk SHP Project Director Management Team Management Project Director • Leading international Programme Design and professional design and Management Construction programme management Support teams Externally Contracted: Designers, Consultants, Technical Specialists, Construction Contractors, etc.

  10. Currently at end of Detailed Design Stage • New permanent office building • Building A – Conference and Offices and Building B – Library Archive • These areas prioritised due to the phasing strategy of utilising completed new building as temporary swing space • Swing space allows the phased moves of staff to vacate areas to enable renovation of existing premises to take place

  11. Indicative Phasing Current BUILDING D BUILDING D BUILDING E BUILDING A BUILDING E BUILDING A BUILDING B BUILDING B BUILDING C BUILDING S Year of Construction Gross Internal Area (m 2 in 2016 / current) BUILDING A 1937 39,746 BUILDING B 1937 15,757 BUILDING C 1937 15,325 BUILDING D 1952 5,088 BUILDING E 1973 79,725 BUILDING S 1937 23,673 179,314

  12. Indicative Phasing 2017 NEW PERMANENT BUILDING INDICATIVE CONSTRUCTION PHASING (2017 - 2023) 2017 2018 2019 2020 2021 2022 2023 New area under Construction (m2) 22,371 22,371 22,371 - - - - Existing areas progressively under Refurbishment (m2) - 37,626 37,626 54,086 97,962 70,919 59,101 Existing area being dismantled (m2) - - - (20,624) (20,624) - GRAND TOTAL (m2) 22,371 59,997 59,997 54,086 97,962 70,919 59,101

  13. Indicative Phasing 2018 BUILDING B NEW PERMANENT ARCHIVES BUILDING BUILDING A CAFETERIA AND CONFERENCE ROOMS INDICATIVE CONSTRUCTION PHASING (2017 - 2023) 2017 2018 2019 2020 2021 2022 2023 New area under Construction (m2) 22,371 22,371 22,371 - - - - Existing areas progressively under Refurbishment (m2) - 37,626 37,626 54,086 97,962 70,919 59,101 Existing area being dismantled (m2) - - - (20,624) (20,624) - GRAND TOTAL (m2) 22,371 59,997 59,997 54,086 97,962 70,919 59,101

  14. Indicative Phasing 2019 BUILDING B NEW PERMANENT ARCHIVES BUILDING Max capacity 1400 workstations BUILDING A CAFETERIA AND CONFERENCE ROOMS INDICATIVE CONSTRUCTION PHASING (2017 - 2023) 2017 2018 2019 2020 2021 2022 2023 New area under Construction (m2) 22,371 22,371 22,371 - - - - Existing areas progressively under Refurbishment (m2) - 37,626 37,626 54,086 97,962 70,919 59,101 Existing area being dismantled (m2) - - - (20,624) (20,624) - GRAND TOTAL (m2) 22,371 59,997 59,997 54,086 97,962 70,919 59,101

  15. Indicative Phasing Approx 550 Staff move 2020 permanently into new building BUILDING D Remainder of staff move in to new building temporarily in phases BUILDING A during renovation OFFICES BUILDING C BUILDING S INDICATIVE CONSTRUCTION PHASING (2017 - 2023) 2017 2018 2019 2020 2021 2022 2023 New area under Construction (m2) 22,371 22,371 22,371 - - - - Existing areas progressively under Refurbishment (m2) - 37,626 37,626 54,086 97,962 70,919 59,101 Existing area being dismantled (m2) - - - (20,624) (20,624) - GRAND TOTAL (m2) 22,371 59,997 59,997 54,086 97,962 70,919 59,101

  16. Indicative Phasing 2021 Staff move back into BUILDING E renovated areas on PARTIAL DEMOLITION completion BUILDING D Remainder of staff move in to new building BUILDING E temporarily in phases BUILDING A RENOVATION during renovation OFFICES BUILDING B BUILDING C BUILDING S INDICATIVE CONSTRUCTION PHASING (2017 - 2023) 2017 2018 2019 2020 2021 2022 2023 New area under Construction (m2) 22,371 22,371 22,371 - - - - Existing areas progressively under Refurbishment (m2) - 37,626 37,626 54,086 97,962 70,919 59,101 Existing area being dismantled (m2) - - - (20,624) (20,624) - GRAND TOTAL (m2) 22,371 59,997 59,997 54,086 97,962 70,919 59,101

  17. Staff move in phases Indicative Phasing temporarily to new building during 2022 renovation BUILDING E PARTIAL DEMOLITION Staff move back into renovated areas on BUILDING E completion RENOVATION BUILDING B INDICATIVE CONSTRUCTION PHASING (2017 - 2023) 2017 2018 2019 2020 2021 2022 2023 New area under Construction (m2) 22,371 22,371 22,371 - - - - Existing areas progressively under Refurbishment (m2) - 37,626 37,626 54,086 97,962 70,919 59,101 Existing area being dismantled (m2) - - - (20,624) (20,624) - GRAND TOTAL (m2) 22,371 59,997 59,997 54,086 97,962 70,919 59,101

  18. Indicative Phasing 2023 Staff move back into renovated areas on completion BUILDING E RENOVATION Remaining staff from off site locations move into new building on completion of project INDICATIVE CONSTRUCTION PHASING (2017 - 2023) 2017 2018 2019 2020 2021 2022 2023 New area under Construction (m2) 22,371 22,371 22,371 - - - - Existing areas progressively under Refurbishment (m2) - 37,626 37,626 54,086 97,962 70,919 59,101 Existing area being dismantled (m2) - - - (20,624) (20,624) - GRAND TOTAL (m2) 22,371 59,997 59,997 54,086 97,962 70,919 59,101

  19. Phase 1 Enabling Works 2017 New Building 2017 – 2019 22,371m2

  20. Scope of Work Excavation of approximately 47,000 m³ of soil • Redistribution of soil throughout the compound • Less costly • Better for environment • Installation of retaining walls • Installation of dewatering system for excavation • Removal and/or protection of trees • Relocation of below grade utilities • Install new storm sewer connection for new building • Removal of existing antennae's • Installation of truck washing facility • Early Works Package

  21. Excavation and Retaining Walls

  22. Soil Relocation

  23. Soil Relocation

  24. New Building

  25. Plaza Design and Campus Connection

  26. Plaza

  27. Roof Terraces

  28. Courtyard

  29. Town Hall Stair

  30. Town Hall Stair with view on the Plaza

  31. FUNCTIONAL FLEXIBLE SUSTAINABLE ENDURING TIMELESS Custom tailored support space per functional needs

  32. Existing Buildings

  33. Cafeteria Extension

  34. Cafeteria Extension

  35. Cour d’Honneur Reabilitation

  36. Collaboration Support Nodes in the Existing Buildings

  37. Collaboration Support Nodes in the Existing Buildings

  38. Collaboration Support Nodes in the Existing Buildings

  39. Conference Rooms Up-grades – Room XII

Recommend


More recommend