cryomodules standardization
play

Cryomodules Standardization S.K. Chandrasekaran International - PowerPoint PPT Presentation

Cryomodules Standardization S.K. Chandrasekaran International Workshop on CM Design & Standardization 09/06/2018 OR 06/09/2018 OR 6 Sept 2018 ??? 2 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design &


  1. Cryomodules Standardization S.K. Chandrasekaran International Workshop on CM Design & Standardization 09/06/2018 OR 06/09/2018 OR 6 Sept 2018 ???

  2. 2 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  3. 3 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  4. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 4 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  5. Outside CM systems • Alignment strategy – Fiducials; HBCAM vs Wire frame – Track during/after cool down? During transport? • Interfaces – RF, Cryogenic, Beam line, Vacuum • Instrumentation – Inside & outside CM – In VTS & test cave (e.g., radiation monitors for FE monitoring) – Connectors and flanges • In-tunnel transport • CM support stands • Performance measurement methods/techniques 5 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  6. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 6 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  7. Cavities – standardization • Interfaces – Lifting lugs Same for SSR1 & SSR2? – Cavity positioning lugs Same for LB650 & HB650? – Coupler & pick up port – Tuner attachment pads • Benefits of standardized parameters: – Tooling required can be the same for the cavities • Only remaining variation would be based on the existing facility – Single design operation and procurement cycle 7 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  8. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 8 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  9. Couplers – standardization • Coupler flange on cavity • Thermal stages Same for SSR1 & SSR2? – 2 K, 5 K, 50 K, 300 K Same for LB650 & HB650? • Thermal straps • Benefits of standardized parameters: – Single design operation – Larger procurement • Coupler procurement can be complex • Validated manufacturing procedures at vendor can be used on larger quantities – Lower QA issues & greater reliability • Potentially lower cost per coupler due to volume discounts 9 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  10. 650 MHz coupler, conventional (backup) design. Adjustable coupling at assembly In backup design the vacuum outer conductor is ‘conventional’ type: SS tube coated by copper. "Experience in the design of fundamental couplers", S. Kazakov, Mumbai 10 9/6/2018

  11. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 11 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  12. 650MHz Tuner LCLS II Tuner Tuner characteristic (based on warm measurements and LCLS II test) Coarse tuner range ~300kHz Coarse tuner res. ~1Hz/step Back/lash coarse tuner ~40Hz Fine tuner range ~6-8um (1.5kHz) Fine tuner resolution ~ 0.1Hz Yuriy Pischalnikov, Resonance Control, September 4, 2018, BARC, India 12

  13. Tuners – standardization • Tuner interface with cavity • Piezo & motors Same for SSR1 & SSR2? • Stiffness of the system Same for LB650 & HB650? • Algorithm development • Benefits of standardized parameters: – Single design operation – Larger procurement • Piezo & motors are long lead and expensive items if purchased individually – Potentially lower cost per item due to volume discounts – Cavity may be different, but tuner the same for algorithm 13 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  14. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 14 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  15. Cavity support system • Spaceframe, strongback are options for PIP-II (not for HWR) 15 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  16. Cavity support system – standardization • Strongback? – Validate in SSR1 Same for SSR1 & SSR2? • Spaceframe? Same for LB650 & HB650? – 650 MHz only • Benefits of standardized parameters: – Design for individual module types would be derivations – Concept validated earlier with one module type – Tooling for assembly will also be similar in concept 16 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  17. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 17 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  18. 3. Cryogenic layout of the cryomodules All cryomodules have the same layout and the same pressure design values. All cryomodules need to be compatible with a fast cool down: • Above 20 K/hour through the Q-disease regime 90 - 175 K. • Above 120 K/hour through the superconducting transition at 9.2 K Pipe B - Pumping line Pipe G - 2 phase He & chimney MAWP: 2.05 bar warm, 4.1 bar cold MAWP: 2.05 bar warm, 4.1 bar cold Pipe I - Helium guard of the current leads MAWP: 4.1 bar Pipe A - 2 K supply Pipe C & D - 5 K line MAWP: 20 bar MAWP: 20 bar Pipe H - Cool down / Pipe E & F - 35-50 K line warm up line MAWP: 20 bar MAWP: 20 bar 18 4-7 September 2018 Vincent Roger | PIP-II Cryomodule Design Overview

  19. Cryogenic system – standardization • Heat exchangers • Valves Same for SSR1 & SSR2? • U-tubes Same for LB650 & HB650? • Benefits of standardized parameters: – Concept validated earlier with one module type – Reliability increased – Vendors validated 19 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  20. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 20 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  21. 21 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  22. Tooling – standardization • Includes cleanrooms, processing facilities, assembly – Each facility to have separate tooling – Interfaces to the components may be standardized • Constraints: – Facility interfaces – may be difficult to standardize across Partners • Benefits of standardized parameters – Tooling changes for facilities (e.g. cleanroom) takes time • Configuration changes can be few weeks to months – Increases reliability – Decreases cost for the facility 22 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  23. Major sub-systems and components • Cavities • Couplers – Coupler installation tooling Validation: horizontal test stand • Tuners • Magnetic shielding • Cavity support system • Cryogenic system within CM Validation: CM test stand – Cryogenic piping – Cryogenic valves • CM assembly tooling • Transportation fixtures & temporary tooling 23 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

  24. Multiple methods available 24 9/6/2018 S.K. Chandrasekaran | International Workshop on CM Design & Standardization

Recommend


More recommend