Penn State AE Senior Capstone PRESENTATION OUTLINE Project Project Introduction Analysis 1: Curtain Wall Timeline Christopher Barron Construction Analysis 2: Green Roof Addition Structural Breadth Management Mechanical Breadth Analysis 3: Prefabrication CM Advisor – Dr. Anumba Summary of Analyses Acknowledgements
Location: Dover Delaware Phase two expansion PRESENTATION OUTLINE Project Introduction • Existing Facility Analysis 1: Curtain Wall Timeline • Podium Building Analysis 2: Green Roof Addition Welcome Center Emergency Structural Breadth Department Mechanical Breadth Integrated Cancer Analysis 3: Prefabrication Center Summary of Analyses • Parking Garage • Bridge Acknowledgements • Central Service Building
Location: Dover Delaware Phase two expansion PRESENTATION OUTLINE Project Introduction • Existing Facility Analysis 1: Curtain Wall Timeline • Podium Building Analysis 2: Green Roof Addition Welcome Center Emergency Structural Breadth Department Mechanical Breadth Integrated Cancer Analysis 3: Prefabrication Center Summary of Analyses • Parking Garage • Bridge Acknowledgements • Central Service Building
Location: Dover Delaware Phase two expansion PRESENTATION OUTLINE Project Introduction • Existing Facility Analysis 1: Curtain Wall Timeline • Podium Building Analysis 2: Green Roof Addition Welcome Center Emergency Structural Breadth Department Mechanical Breadth Integrated Cancer Analysis 3: Prefabrication Center Summary of Analyses • Parking Garage • Bridge Acknowledgements • Central Service Building
Location: Dover Delaware Phase two expansion PRESENTATION OUTLINE Project Introduction • Existing Facility Analysis 1: Curtain Wall Timeline • Pavilion Building Analysis 2: Green Roof Addition Welcome Center Emergency Structural Breadth Department Mechanical Breadth Integrated Cancer Analysis 3: Prefabrication Center Summary of Analyses • Parking Garage • Bridge Acknowledgements • Central Service Building
Location: Dover Delaware Phase two expansion PRESENTATION OUTLINE Project Introduction • Existing Facility Analysis 1: Curtain Wall Timeline • Pavilion Building Analysis 2: Green Roof Addition Welcome Center Emergency Structural Breadth Department Mechanical Breadth Integrated Cancer Analysis 3: Prefabrication Center Summary of Analyses • Parking Garage • Bridge Acknowledgements • Central Service Building
Podium Building PRESENTATION OUTLINE - Function: Hospital Project Introduction - Size: 215,000 sq ft Analysis 1: Curtain Wall Timeline Analysis 2: Green Roof Addition - Building Cost: GMP 65 million Structural Breadth Mechanical Breadth - Construction Dates: Oct 7, 2008 – AUG 19, 2011 Analysis 3: Prefabrication - Delivery Method: Design-Bid-Build CM Agency Summary of Analyses Acknowledgements
Structural System Building Facade PRESENTATION OUTLINE Project Introduction - Braced frame - Schuco FW 60 Mullion- Transom System Analysis 1: Curtain Wall Timeline - Bay size 30’ X 30’ Analysis 2: Green Roof Addition - Masonry brick Structural Breadth - Oversized system Mechanical Breadth - Preformed metal siding Analysis 3: Prefabrication Summary of Analyses Acknowledgements
Problem Statement PRESENTATION OUTLINE Project Introduction - Conflicting waterproofing systems of the three façade systems made it difficult to get the Analysis 1: Curtain Wall Timeline podium b uilding’s enclosure watertight Analysis 2: Green Roof Addition Structural Breadth Goal Mechanical Breadth Analysis 3: Prefabrication - Study the current façade system used Summary of Analyses FW 60 Mullion-Transom - Investigate the reason why making it water tight Acknowledgements became so problematic System - Construct timeline to portray events - Summarize events
Lack of design → - 70% designed when project was bid Issue Discovered PRESENTATION OUTLINE Project Introduction Sequencing Analysis 1: Curtain Wall Timeline - In order for waterproof system to work, the metal Reactions panels needed to be installed before curtain wall Analysis 2: Green Roof Addition - Designed for curtain wall to be installed before metal Structural Breadth panels Mechanical Breadth How Issued Was Solved Analysis 3: Prefabrication Space constraints Summary of Analyses - In order to build to specifications, the brick waterproofing would have needed to be installed in a Acknowledgements Recommendations 5/8” caulking joint
Owner/ Architect Issue Discovered PRESENTATION OUTLINE Project Introduction - Did not want to change curtain walls appearance - Brought skin consultant on Analysis 1: Curtain Wall Timeline → Reactions Analysis 2: Green Roof Addition Whiting-Turner Structural Breadth - Wanted to change to a similar curtain wall system Mechanical Breadth - Would have eliminated tying ABV into brick How Issued Was Solved Analysis 3: Prefabrication - Less fabrication time Summary of Analyses Acknowledgements Recommendations
Watertight Wall was Erected Issue Discovered PRESENTATION OUTLINE Project Introduction - Built behind curtain wall - Kept project’s schedule critical path on track Analysis 1: Curtain Wall Timeline Reactions Analysis 2: Green Roof Addition Additional Waterproofing Measures Taken Structural Breadth Mechanical Breadth → - AVB wrapped into all sides of the building How Issued Was Solved Analysis 3: Prefabrication - Stainless steel flashing - Any further gaps were caulked shut Summary of Analyses Acknowledgements Recommendations
Issue Discovered PRESENTATION OUTLINE Summary Project Introduction Analysis 1: Curtain Wall Timeline - Over $400,000 in design changes added Reactions - Additional 6 Weeks Added to the Project Schedule Analysis 2: Green Roof Addition Structural Breadth Recommendations Mechanical Breadth How Issued Was Solved Analysis 3: Prefabrication - Better collaboration between all parties Summary of Analyses - Switch to alternative system - Bring CM onto project earlier Acknowledgements → Recommendations
PRESENTATION OUTLINE Problem Statement Project Introduction - Few sustainable ideas implemented on the Bayhealth Analysis 1: Curtain Wall Timeline Medical Center Expansion Analysis 2: Green Roof Addition Structural Breadth Goal Mechanical Breadth - Study green roof technology, and then determine its Analysis 3: Prefabrication cost effectiveness on this project - Located on the Third Floor Summary of Analyses Acknowledgements - Total 28,000 SQ FT
System Chosen PRESENTATION OUTLINE Growth Media Project Introduction Manufacturer - Blend of organic Analysis 1: Curtain Wall Timeline - GreenGrid roofing systems and inorganic Analysis 2: Green Roof Addition components Structural Breadth Module Mechanical Breadth Vegetation - 2’X2’X4” 100% Pre -consumer recycled Analysis 3: Prefabrication polyethylene trays - Perennials, grasses, Summary of Analyses shrubs, etc Acknowledgements Weight Modular Green Roof System - 18 to 22 lbs/ft 2 (Wet)
Existing Roof Detail Current Roof Slab PRESENTATION OUTLINE Roof Loads Project Introduction - Composite deck 3- ¼” LW - The dead - Live = 25 PSF Analysis 1: Curtain Wall Timeline concrete load is less - Dead = 15 PSF Analysis 2: Green Roof Addition than the snow - Snow = 24 PSF - 18 gauge galvanized metal load therefore Structural Breadth decking - Green Roof = 20 PSF the snow load Mechanical Breadth - Conc. Slab = 24 PSF is used - 3” to 1.5” tapered insulation Analysis 3: Prefabrication Summary of Analyses Total = 94 PSF - 5/8” cover board Acknowledgements - Single ply EPDM membrane
Bay One Bay Two Bay Three Demension 30'X32' 30'X26' 30'X32' PRESENTATION OUTLINE Project Introduction Beam Size W18X35 W14X22 W30X108 Shear = WL/2 Analysis 1: Curtain Wall Timeline Beam Spacing 10' 7.5' 10' Analysis 2: Green Roof Addition Moment = WL^2/8 Shear 15.04 kip 9.17 kip 15.04 kip Structural Breadth Mechanical Breadth Shear Capacity 159 kip 96 kip 488 kip - All beams were considered simply supported Analysis 3: Prefabrication - Bare beam capacity was used despite a composite Moment 120.32 kip-ft 58.96 kip-ft 120.32 kip-ft Summary of Analyses beam system Acknowledgements Moment 249 kip-ft 125 kip-ft 1300 kip-ft Capacity - Girders were also determined to be sufficiently sized
Recommend
More recommend