cheltenham transport plan phase 4
play

Cheltenham Transport Plan Phase 4 June December 2018 review - PowerPoint PPT Presentation

Cheltenham Transport Plan Phase 4 June December 2018 review Overview Implementation of CTP in phased approach approved in 2015. Analysis of traffic flows undertaken after completion of each Phase Report produced and


  1. Cheltenham Transport Plan – Phase 4 June – December 2018 review

  2. Overview • Implementation of CTP in phased approach approved in 2015. • Analysis of traffic flows undertaken after completion of each Phase • Report produced and discussed with Lead Cabinet Member.

  3. Feedback to date Total of 798 submissions to GCC website: 376 formal representations; 422 general enquiries (comments / questions). GCC respond to ‘what’ enquiries, CBC respond to ‘why’ enquiries. General themes across all correspondence: – Access for businesses on Clarence Parade and the western end of Clarence Street; – Blue Badge Holder access to Pittville Street; – Concerns / comments on traffic increases on other routes around the town and increases in journey time. Streets mentioned include St. George’s Street and Rodney Road; and – Signage comments were primarily recorded in the initial month, but these have decreased following the additional traffic management introduced in early August;

  4. Traffic Flow Monitoring Overview • 26+ Sites across the town. Mixture of fixed counters & temporary RADAR counters. • Sites on main roads and minor roads which may experience changes in flow / had been flagged by public. • Baseline data collected during November 2015 • Average 24 hour two-way flow used as baseline position as scheme is in place 24/7

  5. Monitoring Site Map A4019 All Saints Rd Waitrose Trial Restriction Extents Albion St Rodney Rd Bath Rd Imperial Sq College Rd A40

  6. Phase 4 Monitoring • Three data sets collected to date: – July 2018 (Primarily monitoring for any immediate issues) – September 2018 (first neutral collection period after start) – November 2018 (To provide comparison to baseline data)

  7. Temporary Site Data 2015 -2018 Average 24 hour two-way flow at each site 12000 10000 8000 Nov 15 (Baseline) 6000 Sept 16 (Post-Phase 1) May 17 (Post-Phase 2) Feb 18 (Post-Phase 3) 4000 Sep-18 Nov-18 2000 0

  8. Fixed Site Data 2015 -2018 Average 24 hour two-way flows at each site 18000 16000 14000 12000 10000 Nov 15 (Baseline) Sept 16 (Post-Phase 1) 8000 May 17 (Post-Phase 2) 6000 Feb 18 (Post-Phase 3) Sep-18 4000 Nov-18 2000 0

  9. Phase 4 Monitoring Key Areas • Northbound routes (St. James Sq, Ambrose St, St. George’s St) • East (Rodney Road, High Street, Winchcombe Street S) • Data collaborates feedback from public • Growth between 20% and 35% but from a relatively small baseline • Mitigation measures being considered

  10. Proposed Revisions to the Trial Address key themes raised in feedback: 1. Revised restriction. Maintains overall scheme objectives, and removes Clarence Parade / Clarence Street from the restrictions. 2. Additional blue badge bays in Winchcombe Street. Additional bays locations identified immediately north of High Street

  11. Additional Works • Investigation into options for traffic calming on Rodney Road; and • Investigation into wider directional signing; and • Separate longer term improvement project for A4019 corridor (2020+)

  12. Timeline/Next Steps • Mitigation measures likely to be install in April/May 2019 • 6 month consultation period following changes • TRO Committee to review experimental TRO - November or December 2019.

  13. Headline impacts of Cheltenham Transport Plan First phase – Albion Street • Main beneficiary is service B Charlton Kings – Swindon Village with 7,000 users per week • Shorter route via Albion Street saves 1,500 miles p.a / 190 gallons of diesel • Route time saving c2 minutes from Charlton Kings; greater saving at peak times

  14. Headline impacts of Cheltenham Transport Plan Current phase – Boots Corner • Since trial began in June 2018 passenger journey numbers in Cheltenham up 5,000 per week • This is 4% growth against a national picture of 2% decline and supports GCC Local Transport Plan target to maintain bus usage • Cheltenham bus punctuality up to 93.1% from 91.5% over 50,000 miles in Cheltenham per week • November 2018 weekend races meeting; buses taking 15% less time (8 mins) to travel from the Racecourse to the town, station and back to the Racecourse to undertake their next journey

  15. Significant Positive Impacts • 85% drop in traffic at Boots Corner, - reduction of 800 vehicle per hour • 700 additional pedestrian movements per hour • 4% more bus passengers – 5,000 passenger journeys per week • Bus punctuality improvements • Number of cyclists tripled • 70% increase in wheelchair movements • 531 direct jobs generated

Recommend


More recommend