ANNIS ROAD PRV STATION AND FIRE MAIN REPLACEMENT PROJECT - PowerPoint PPT Presentation

ANNIS ROAD PRV STATION AND FIRE MAIN REPLACEMENT PROJECT NEIGHBORHOOD MEETING OCTOBER 14, 2017 PROJECT SUMMARY Project Includes: 6,650 linear feet of new 8 and 10 ductile iron water main to replace existing 6 water main


  1. ANNIS ROAD PRV STATION AND FIRE MAIN REPLACEMENT PROJECT NEIGHBORHOOD MEETING OCTOBER 14, 2017

  2. PROJECT SUMMARY  Project Includes:  6,650 linear feet of new 8” and 10” ductile iron water main to replace existing 6” water main  Installation of a new pressure reducing valve (PRV) in underground vault  Temporary relocation of 98 private water services  Replacement of 98 water meter boxes 2  Replace/relocate 18 fire hydrants

  3. PROJECT BENEFITS  Improves public safety  Improves fire flow availability to residential neighborhoods  Adds new hydrant locations to improve coverage  Replaces aging infrastructure  Upgraded pipe materials 3

  4. PROJECT IMPLEMENTATION  Divided into Eastern and Western Sections  Each section completed sequentially by phase (W1, W2, etc.)  Temporary water bypass system will be installed to maintain water service during construction  Service will be interrupted to connect to temporary bypass  Staging at Firth Park parking lot and Brisbane Fire Station back lot 4

  5. CONSTRUCTION CHALLENGES  Narrow roads with limited access  Steep terrain  Many other existing utility lines (sewer, storm, gas)  Hard bedrock close to surface 5

  6. PROJECT IMPACTS  Road Closures Limited to 500 feet per day  Contractor must provide 72 hours advanced notice  Traffic must be restored at the end of the work day  Contractor must provide access for emergency  vehicles at all times Trash pickup limitations (City will look to adjust  prior to construction) Delivery service daytime interruption (USPS, FedEx,  UPS, On-Track, etc.)  Water service disruptions Service must be restored within 8 hours  Contractor must provide 72 hours advanced notice   Temporary Water Bypass Installed in gutter or along side of road  Ramps will be installed at each driveway  6

  7. SCHEDULE  Start of Construction planned for Spring 2018  Duration estimated to be 9 months PUBLIC OUTREACH  Website – http://brisbaneca.org/fire-main-replacement-project  Social Media – Nextdoor, Facebook, etc.  Friday Website Blog – updates on significant work  Direct Mail  Door Hangers  STAR 7