ANIMP WORKSHOP 22 November 2019
Ansaldo Energia support to SA power needs – a Case Study for Avon Power Plant 02/12/2019 2
ANSALDO ENERGIA in AFRICA A success story… 02/12/2019 3
Ansaldo Energia in Africa References, included recent awards COUNTRY SITE TYPE POWER [MW] ALGERIA AIN DJASSER OC - AE94.2 700 BATNA OC - AE94.2 350 HAMMA OC - AE94.3A 450 HASSI MESSAOUD OC - AE94.3A 650 LABREG OC - AE94.2 500 LARBAA OC - AE94.2 650 M'SILA OC - AE94.3A 550 TERGA CC – GT26 1200 CONGO POINTE NOIRE OC - AE94.2 530 EGYPT 6TH OCTOBER OC - AE94.2 1200 AL SHABAB CC - ST 1500 ALMAHMOUDIA OC - AE94.2 350 BANHA CC - ST 800 EL ATF CC - ST 800 GIZA NORTH CC - ST 2250 SIDI KRIR CC – ST 800 WEST DAMIETTA CC – ST 750 GHANA EFFASU MANGYEA OC – AE64.3A 130 SOUTH AFRICA AVON OC - AE94.2 680 DEDISA OC - AE94.2 340 TUNISIA RADES ST 350 SOUSSE C & D CC - AE94.3A 800 MORNAGUIA OC /AE94.3A 625 Branch office GHANNOUCH CC – GT26 400 ZIMBABWE MUTARE OC – AE64.3A 120 Installations TOTAL 17475
Ansaldo Energia in South Africa Recent successful experience: open cycle peaking plants Commercial Long Term Final MW AEN role Site GT Type Units Operation Service Customer Plant Date Agreement DEDISA PEAKING Port EPC Leader AE94.2 2 340 2015 15 years POWER (PTY) LTD Elizabeth AVON PEAKING EPC Leader Durban AE94.2 4 680 2016 15 years POWER (PTY) LTD Ansaldo Energia South Africa (Johannesburg) AVON 680MW PEAKING POWER PLANT DEDISA 340MW PEAKING POWER PLANT
DEDISA 340MW Peaking Power Project Port Elizabeth, 2 x 170MW Units • Open Cycle, Turnkey EPC Project • Greenfield Site • Gas Turbines: 2x170MW Ansaldo Energia AE94.2 • Start of Site Activities: September 2013 • Commercial Operation: September 2015 • Long Term Service Agreement: 15 years
AVON OCPP Peaking plant VIDEO 02/12/2019 7
AVON 680MW Peaking Power Project Durban, 4 x 170MW Units • Open Cycle, Turnkey EPC Project • Greenfield Site • Gas Turbines: 4x170MW Ansaldo Energia AE94.2 • Start of Site Activities: December 2013 • Commercial Operation: July 2016 • 15 years Long Term Service Agreement • Manpower (Peak / Total Work hours) > 1500 / 4,4million • Total local black employees: around 3000 • 75% skilled, 99% unskilled hired from local community
AVON 680MW Peaking Power Project Plant final layout Administration Workshop Outfall / Stilling building building Connection to Basin National Grid Power Block External Fences Landscaping Internal Roads Fuel Storage Fuel Station GT Unit #4 GT Unit #3 GT Unit #2 Gate House & Main Entrance GT Unit #1 Free area for future CC expansion
Why choose an Add-on solution moving to combined cycle power plant? Open cycle have been often built as a fast track solution responding to power demand , lower costs and flexible solution Open cycle are anyway unable to meet current and future efficiency and environmental compliance needs Add-on solution enable a fast switch to combined cycle operation , proven to deliver better performance , as an attractive option to meet high demand needs and environmental requirements COMPANY CONFIDENTIAL
Add-on – Main features Nearly 50% more power with the same fuel (conversion to gas) and efficiency rates of 60% and more Significantly reducing the plant environmental impact to achieve emissions reduction goals in the energy mix with renewables High degree of flexibility in operation with start up time reduced down to 30 min (hot condition) and close to 15 min for simple cycle Steam supplied by HRSG can also be used to feed other applications (e.g. district heating, industrial applications) Computer-controlled plant start-up and shut-down sequences, plant coordinated control systems, with fully automated plant management guarantee maximum performance . COMPANY CONFIDENTIAL
Add-on – Ansaldo Energia main reference projects, EGYPT 6 th October • 4 x 150 MW AE94.2 + 1 x 340 MW AE MT20 • Ansaldo Energia EPC contractor Al Shabab • 2 x [4 x 125 MW GE + 1 x 270 MW AE MT20] • Ansaldo Energia STG power block , air cooled condenser and electrical auxiliaries West Damietta • 4 x 125 MW GE + 1 x 270 MW AE MT20 • Ansaldo Energia STG power block, air cooled condenser and electrical auxiliaries COMPANY CONFIDENTIAL
AVON ADD-ON MAIN PARAMETERS AND FIGURES Main requirement: gas availability and GTs conversion to gas First option: straight add-on (all 4 GTs) or modular (2 phases, 2 GTs per phase) Second option: configuration, 4+1 (only for straight add-on) or twice 2+1 GT power increase: during gas conversion a new set of blades can be installed to increase GT output (indicative figure is 8 MW per unit at ISO condition) The magical rule: 2 to 1… it means that in a combined cycle the steam turbine power is around 50% of the GTs overall power… which means … Overall Power Output increases by roughly 50% compared to the current one Overall efficiency drastic improvement as the same number of molecules is consumed to generate a higher output Emissions level within WB values with no water injection Additional benefits • Water saving (today DI water is made up from potable water) • Fuel supply: non need of truck deliveries • Safety: road circulation, better environment • Workforce: consistent increase in local jobs (pipeline, additional equipment in the power plant) DISCLAIMER The information and data provided in this presentation are for reference only and are not binding, and do not constitute a promise of sale, warranty, performances, merchantability. AnsaldoEnergia waives any liability arising from the use of such information and data by any third party.
THANK YOU!! internal/confidential/strictly confidential* 02/12/2019 14