Sizewell A report to SSG Allen Neiling Closure Director Feb 2019 Safety and compliance We have had two recordable injuries since the last meeting False widow spider bite Slip in wet conditions No environmental events


  1. Sizewell A report to SSG Allen Neiling – Closure Director Feb 2019

  2. Safety and compliance • We have had two recordable injuries since the last meeting – False widow spider bite – Slip in wet conditions • No environmental events

  3. Management of Bradwell • Bradwell is now in the Care and Maintenance (C&M) phase - a year earlier than planned • First time a UK commercial reactor site has moved into C&M • Extensive handover programme completed with Sizewell A - now managing the site following regulatory approval • On-going site inspections and ILW being received from Dungeness A

  4. Plant and Structures Programme update • Removal and demolition of the National Grid substation building - – Hazard removal commenced (asbestos and redundant equipment) – Demolition expected to start in April 2019 4

  5. Ponds Programme update • Successful removal of temporary shielded storage container (TSSC) • Completed ILW skip basket removal • Retrieval of intermediate level waste and low level waste skips from the pond now commenced

  6. Asset Care Projects • Asbestos management continues on site – before and after • Cladding repairs continue on the reactor buildings 6

  7. Socio-economics – 2018/19

  8. Socio-economics - contacts For further information and to check if you are eligible to apply go to: www.magnoxsocioeconomic.com Contact Steve Payne for ‘good neighbour’ applications or Haf Morris for potential applications over £1,000 The Magnox Socio-economic Plan 2016-19 (2018 Revision) has been reviewed and recently issued. It is available on the Magnox website www.magnoxsites.com/publications

  9. Thank you • Any questions?