A Staged Approach to the Design of a Nuclear Reactor Andrew Shaw - Oct 15, 2015 00/2015
Outline 2 • Hatch • Our MSR • Project Staging 00/2015
HATCH 3 CANADA Calgary, Alberta St. John’s, Newfoundland & Labrador Halifax, Nova Scotia Sorel-Tracy, Québec Mississauga, Canada Sudbury, Ontario Montréal, Québec Toronto, Ontario EUROPE Niagara Falls, Ontario Vancouver, British Columbia Oakville, Ontario Winnipeg, Manitoba London, England Saskatoon, Saskatchewan Moscow, Russia St. Petersburg, Russia CHINA Beijing Shenyang Shanghai INDIA USA New Delhi Amherst, New York New York, New York MIDDLE EAST Baltimore, Maryland Pensacola, Florida Boston, Massachusetts Phoenix, Arizona Abu Dhabi, UAE INDONESIA Buffalo, New York Pittsburgh, Pennsylvania Al Khobar, Saudi Arabia Jakarta Cleveland, Ohio Sacramento, California Sohar, Oman Denver, Colorado San Diego, California Houston, Texas San Francisco, California SOUTH Millburn, New Jersey Seattle, Washington AMERICA NEW Tampa, Florida SOUTH AFRICA CALEDONIA Antofagasta, Chile Johannesburg Nouméa Belo Horizonte, Brazil Pretoria Lima, Peru Cape Town Rio de Janeiro, Brazil AUSTRALIA Santiago, Chile Adelaide Newcastle São Luís, Brazil Brisbane Perth São Paulo, Brazil Gladstone Townsville Mackay Wollongong Melbourne 00/2015
HATCH Technologies: Furnace 4 00/2015
HATCH Technologies: Autoclave 5 00/2015
N-Solv 6 00/2015
Outline 7 • Hatch • Our MSR • Project Staging 00/2015
HATCH Technologies: MSR 8 Cooler Salt Hotter Salt Salt-salt heat exchanger Piping & Pumps DMSR Core Cooler Salt Hotter Salt 00/2015
HATCH Technologies: MSR 9 00/2015
HATCH Technologies: MSR 10 00/2015
HATCH Technologies: MSR 11 00/2015
Outline 12 • Hatch • Our MSR • Project Staging 00/2015
A Staged Approach 13 00/2015
A Staged Approach 14 00/2015
15 Stage Activity Identify Ongoing Opportunities Define FEL 1 Options Select Option FEL 2 & Plan Develop FEL 3 Design Buy & Install FEL 4 Equipment 00/2015
16 Symphony Analogy Stage Activity Symphony Analogy Identify Ongoing Opportunities Define FEL 1 Options Select Option FEL 2 & Plan Develop FEL 3 Design Buy & Install FEL 4 Equipment 00/2015
17 Our Reactor Stage Activity Identify Ongoing Opportunities Gate Define FEL 1 Options Gate Select Option FEL 2 & Plan Gate External Investment Develop FEL 3 Design Buy & Install FEL 4 Equipment 00/2015
18 Human Nature! Stage Activity Identify We already have a Ongoing Opportunities list of good ideas Define We already have a FEL 1 Options design Select Option This needs to be FEL 2 & Plan finished fast! Develop The project is FEL 3 Design ready to execute Buy & Install FEL 4 Equipment 00/2015
19 Human Nature! Stage Activity Identify We already have a Bad ideas will be Ongoing Opportunities list of good ideas developed Define Sub-optimal ideas We already have a FEL 1 Options design will be developed Select Option This needs to be The project will FEL 2 & Plan finished fast! take more time Develop The project is Capital will be FEL 3 Design ready to execute tied up Buy & Install FEL 4 Equipment 00/2015
20 Discipline Stage Activity Identify Ongoing Opportunities Define FEL 1 Options It may be Select Option necessary to FEL 2 & Plan go backwards Develop FEL 3 Design Buy & Install FEL 4 Equipment 00/2015
21 Thinking : Doing Stage Activity Identify The design Ongoing 90% : 10% Opportunities process (It can’t be managed like a Define FEL 1 80% : 20% FEL 3/4 project) Options Typical Select Option FEL 2 50% : 50% project & Plan planning Develop FEL 3 20% : 80% Typical Design project management Buy & Install FEL 4 10% : 90% Equipment 00/2015
Recap 22 • Hatch • Our MSR • Project Staging 00/2015
Recommend
More recommend