A Developers Experience in the World of Brownfields Cory Heitz - PowerPoint PPT Presentation

A Developers Experience in the World of Brownfields Cory Heitz Garrett LLC Garretts First Brownfield Former Fansteel Manufacturing Plant Lexington, KY 98,000 sq/ft on 8 acres WHY DID WE PURCHASE THIS SITE? Company paid us


  1. A Developer’s Experience in the World of Brownfields Cory Heitz Garrett LLC

  2. Garrett’s First Brownfield  Former Fansteel Manufacturing Plant  Lexington, KY  98,000 sq/ft on 8 acres WHY DID WE PURCHASE THIS SITE?  Company paid us to take it  Location/Zoned I-2  Company had other available properties

  3. Garrett’s First Brownfield (cont) OTHER FACTS  $1M+ to rehab building and remediate site  PCBs and TCEs removed, still monitoring  Fought for $150k tax credit from State of Ky  Have tenant signed to a 10-year lease

  4. Our First Brownfield (cont) LESSONS LEARNED  Demo or rehab a building?  Hire specialized legal staff i.e. environmental law  Connected environmental engineers

  5. 1st Clean Ohio Project  Former Howard Paper Plant  Edwin C Moses Blvd in Dayton, OH  197,000 sq/ft on 4.5 acres WHY DID WE PURCHASE THIS SITE?  Great price and excellent location  Improve Downtown Dayton  Environmental was manageable  Clean Ohio grant potential

  6. 1st Clean Ohio Project OTHER FACTS  Sinclair College signed on as end user  Received Covenant Not to Sue in July 2012

  7. 1st Clean Ohio Project LESSONS LEARNED  Large vs Small contractors  I-75 construction on Edwin C Moses ramps  Build relationship w/ local and state officials

  8. 2nd Clean Ohio Project  Former Frick Gallagher Plant  Wellston, OH  100,000 sq/ft on 6.5 acres WHY DID WE PURCHASE THIS SITE?  Saw potential once site was remediated/demoed  Assist city by removing eyesore/safety hazard  Clean Ohio grant potential

  9. 2nd Clean Ohio Project (cont) OTHER FACTS  Once we get Covenant Not to Sue we will transfer property to city. We will receive a tax credit.  Break even project

  10. 2nd Clean Ohio Project (cont) LESSONS LEARNED  No more rural projects due to marketability  Distance to a major city: Cincinnati 2.5 hrs  Don’t spread ourselves too thin: concentrate in the Dayton and Cincinnati region

  11. 3rd Clean Ohio Project  Former Hexion Chemical Site  Glendale-Milford Rd, Village of Woodlawn  145,000 sq/ft on 13.5 acres WHY DID WE PURCHASE THIS SITE?  Location, Location, Location!!!  Clean Ohio grant potential

  12. 3rd Clean Ohio Project (cont) OTHER FACTS  Currently awaiting Covenant Not to Sue LESSONS LEARNED  Leadership transition in village

  13. Dayton Land Bank Properties 824 Leo St, Rita Construction Site  Taxes not paid since 2009, $170k owed  Received from Land Bank (LB) at no cost except for legal expenses  Abated asbestos and demoed structure  Have contract to sell 4 of 10 acres to future taxpayer

  14. Dayton Land Bank Properties 1020 Valley St, Dayton Electro Plate  Plant vacant 16 years  Owed over $500k in taxes  Consolidated 14 tracts into 1  Cut brush, tore structures down, improved neighborhood  Received Clean Ohio grant for Phase II

  15. Dayton Land Bank Properties 1801 Home Ave, MPT Real Estate Building  Owed over $160k in taxes  Cut brush, fixed fence, cleaned grafftti  Rehabilitating building

  16. Dayton Land Bank  Currently working on 8 deals through LB  Excellent opportunities  Educating other communities

  17. Lessons Learned  State assistance available; learn about them all  More to job than just being a specialist  Relationships ensure success

  18. The Future  Clean Ohio Brownfield Fund?

  19. Contact Cory Heitz Garrett LLC 859-317-1166 Coryheitz@gmail.com www.garrettworks.com

  20. Questions?